Expressindia » Story

Metro not in July but December end

Font Size

Swapnil Rawal

Posted: Oct 26, 2009 at 0346 hrs IST

Mumbai People expecting to take a metro ride in Mumbai by the end of July would have to wait at least till December next year, as construction is unlikely to be completed by the deadline set by the implementing agency, the Mumbai Metropolitan Region Development Authority (MMRDA).

The Versova-Andheri-Ghatkopar metro corridor is being constructed by Mumbai Metro One Pvt Ltd, a special purpose vehicle formed by Reliance Infrastructure, MMRDA and Veolia Transport. As per the contract, MMOPL has to construct the corridor in five years. But MMOPL had set itself a deadline to operationalise the corridor by the end of July 2010.

According to Ashwini Bhide, Joint Metropolitan Commissioner, MMRDA, around half of the civil construction on the 11.4 km corridor has been competed. “Over 50 per cent of the work on the corridor is over, including civil construction; girder launching has begun in sections. Simultaneously, other works of signalling, advanced ticketing system, etc are under way,” Bhide said.

Asked whether MMOPL will be able to commission the corridor by July-end, Bhide responded, “It will be commissioned by December-end...there are delays on the ground as permission from railways for construction over Andheri railway lines is pending. But it cannot be called a delay since construction period as per the contract is five years.”

The delay in construction of the special bridge over the railway lines near Andheri station was due to railway authorities allowing construction only for two-three hours—when train services are shut. A senior official added, “Two-three hours of construction time would not be sufficient to finish the work in time. Therefore, talks with railway authorities would be needed to allow construction throughout while safety of people and railway property would be taken care of,” said an official requesting anonymity.

Meanwhile, the first batch of air-conditioned Metro rakes built in China will arrive by January 2010. Initially there will be only four coaches in a rake, with aerodynamic nose, while two more coaches would be added after a couple of years. They also said the rakes would have only one class and frequency of trains would be five minutes which would decrease gradually after induction of more rakes on the corridor.

Discuss this story on expressindia forums
Post Comments
Name* Email ID*
Subject* Country*
Message*
Characters remaining
 
TERMS OF USE: The views, opinions and comments posted are your, and are not endorsed by this website. You shall be solely responsible for the comment posted here. The website reserves the right to delete, reject, or otherwise remove any views, opinions and comments posted or part thereof. You shall ensure that the comment is not inflammatory, abusive, derogatory, defamatory &/or obscene, or contain pornographic matter and/or does not constitute hate mail, or violate privacy of any person (s) or breach confidentiality or otherwise is illegal, immoral or contrary to public policy. Nor should it contain anything infringing copyright &/or intellectual property rights of any person(s).
I agree to the terms of use.

Latest News

Business

Showbiz

Sports

Scrap Liberhan report lock, stock and barrel: BJP

Rao govt had made wrong political judgement: PC

KCR's health may decline rapidly: Doctor

Pak Major key link between Headley, terrorist leaders

‘Hiring may return to pre-recession pace soon’

India, Russia end stalemate over Gorshkov's price deal

Coordinated attacks in Baghdad kill at least 112

More
Featured Services
© 2009 The Indian Express Limited. All rights reserved
The Indian Express Group | Advertise With Us | Privacy Policy | Feedback | Work With Us | Site Map