|
No need to re-examine Dabhol project, says SC
Sunil Jain
NEW DELHI, May 2: The controversial $1.2 billion Dabhol Power project of the
Enron Power Corporation received a big boost when the Supreme Court today
declined to re-examine the project and its renegotiation by the Maharashtra
government. The court, however, came down on the State government's changing
stance on the project.Responding to a Public Interest Litigation (PIL) filed
by the Centre of Indian Trade Unions (CITU), the court said, ``It is not in
the public interest to examine the authority of the contract at this
stage.'' It ruled that the question raised by CITU regarding the validity of
the project as a result of the actions of the state government did not
require examination at the present stage as it had already been gone into by
Bombay High Court.
This opinion was expressed by a three-judge bench comprising Chief Justice
JS Verma, Justice Sujata V Manohar and Justice M Jagannatha Rao.
With this, what could be the last legal hurdle in the way of the project has
been removed. The Dabhol Power Company president and managing director
Sanjay Bhatnagar said the company was delighted with Supreme Court decision
and hoped it would put an end to litigations against the project. ``We hope
this will end all frivolous litigations against the project and we can
concentrate on the project and commission the plant well ahead of schedule,
'' he said.
The CITU PIL came in the wake of the re-negotiation of the project by the
Maharashtra government last year, after it had been cancelled. CITU had
alleged that though the project had been re-negotiated, the state government
had still given Enron undue concessions. As such, it had argued, that the
project should once again be re-examined and the various irregularities in
its awarding be looked at -- and that the role of the Maharashtra government
also be examined.
While the government had cancelled the project because it felt it was
heavily loaded in favour of Enron, the subsequently re-negotiated project
didn't extract too many concessions from Enron despite its assertions to the
contrary. A large part of the so-called concessions that the government had
got, in fact, were due to restructuring as well as repackaging of the
project. In the event, it was evident that many of the so-called concessions
could have been got even before the project was cancelled, and arbitration
proceedings begun. So while the State Government had claimed that it had
extracted huge concessions from Enron in the 695 MW Phase 1 of the project,
the fact is that Enron offered no concessions in Phase 1. The concessions
were in fact wrought by expanding the size of the project to 2,450MW- this
was done by enlarging the size of phase 1 to 740 MW and including Phase 2 as
well. Once the project's size was increased, Enron passed on the benefits of
economies of scale to the Maharashtra government. Besides, falling equipment
costs internationally also helped.
Further, in order to make its renegotiated project look good, the
Maharashtra government also decided to spin off part of the old project into
a new one. The $495 million regasification project of the earlier Phase 2
was spun off into a new company and hence it was made to look as if savings
of $495 million had been achieved in the overall new project. Actually
Copyright © 1997 Indian Express Newspapers (Bombay) Ltd.
|